The Challenge
Operating offshore Congo, Claxton were engaged to carry out the internal cutting of eight subsea piles, each with a diameter of 2.6 m. All cutting and recovery operations were performed from a heavy lift vessel (HLV), with cuts required to be executed internally at 0.5 m above the mudline. Due to variations in pile installation depths, cut elevations differed for each pile. This required adjustments to the equipment setup for each operation, as well as careful control of the cutting process to ensure no damage to the adjacent subsea template.