Skip to content
Contact us

Vessel Based Pile Severance

PHOTO 2025 07 10 11 46

The Challenge

Operating offshore Congo, Claxton were engaged to carry out the internal cutting of eight subsea piles, each with a diameter of 2.6 m. All cutting and recovery operations were performed from a heavy lift vessel (HLV), with cuts required to be executed internally at 0.5 m above the mudline. Due to variations in pile installation depths, cut elevations differed for each pile. This required adjustments to the equipment setup for each operation, as well as careful control of the cutting process to ensure no damage to the adjacent subsea template.

The Solution

Claxton provided our Internal Leg Cutter (ILC), a robust, reliable and field proven tool used as part of our xcalibre Abrasive Cutting Solutions package. The ILC has a fixed upper body, a rotating lower nozzle assembly and centralising pins, for optimum tool alignment and stability before and after cutting. The tool was deployed into the pile using the vessel crane until the spreader beam landed on the pile top, while the rigging was adjusted to achieve the required cut elevation. Using abrasive material, a full 360° circumferential cut was completed on the pile, while ensuring no damage to the surrounding subsea template.

The Result

Claxton successfully completed the internal cutting and recovery preparation of all eight subsea piles safely and efficiently. The flexibility of the ILC and adjustable deployment arrangement enabled precise positioning of each cut at the required elevation, 0.5 m above the mudline. The abrasive cutting process delivered clean, full circumferential cuts on every pile while maintaining protection of the adjacent subsea template throughout operations. By utilising Claxton’s xcalibre solution with proven cutting technology and experienced offshore execution, we minimised operational risk, reduced vessel time and ensured the project was completed in line with the client’s requirements.

PHOTO 2025 06 28 16 52 10 aspect ratio 31
xcalibre Abrasive Cutting Solution on vessel deck pre deployment
ILC Pulling out of 2.6m pile aspect ratio 31
ILC Deployment into 2.6m Pile
Cut Section Being Recovered aspect ratio 31
Cut section being recovered
PHOTO 2025 07 10 11 46 23 aspect ratio 31
Longer pile sections after laydown on barge
PHOTO 2025 07 10 11 46
  • 40m Water Depth
  • 2.6m Pile Diameter
  • 50mm Wall Thickness
  • 8 Abrasive Cuts completed
  • 8 Hours - Average Cut Time