Skip to content
Contact us

Rigless Platform Conductor Cutting

IMG 20250926 WA0014

Project details

Download PDF

Rigless Conductor Cutting with xcalibre

Xcalibre acs

The Challenge

An operator in the Norwegian North Sea required the removal of 24 conductors including six tie-back wells which were installed in a subsea template. The 18 platform wells had a 20”x26” profile, with the tie backs being 20”x30” and one single 26”. All wells were to be severed 2 meters below the mudline.

The tie-back wells introduced significant technical constraints:
• The cutting manipulator had to pass through a 15in restriction inside the tie-back connector, which was present in all tie-back wells, before expanding into a 19in wellbore.
• A second cut was required above the tie-back connector to allow the wells to be recovered together with the subsea template.
• The client required both cuts to be completed in a single deployment for operational efficiency.
• On the single string well the cutting manipulator still had to pass the 15in restriction, while still being capable of seating securely inside a 26-inch conductor.

Additional project complexities included:
• Deployment from a custom Conductor Guide Frame positioned 48 meters above sea level.
• 175 meters water depth.
• 29 meters conductor stick-up, resulting in a total cut depth of 206 meters from wellhead to cut elevation, making these the deepest platform wells ever cut using xcalibre - Claxton’s Abrasive Cutting Solution.
• During annulus venting, a small hydrocarbon-like substance was observed. Before cutting operations could proceed, the entire 206-meter annulus column had to be confirmed hydrocarbon-free to eliminate environmental risk.

Standard tooling was not suitable due to the limited packer expansion range and internal diameter restrictions within the tie-back connectors.

The Solution

Tooling Innovation - Although Claxton’s xcalibre cutting system is field-proven to 450m water depth, the tie-back connector restriction and multi-diameter cutting requirement necessitated a redesign of the cutting manipulator.

Claxton delivered:
• Re-engineered the internal drive unit to integrate an inflatable packer system used in SWATTM (Suspended Well Abandonment Tool).
• Achieved the required expansion range while maintaining the 15-inch OD restriction.
• Enabled cutting of 20” x 30” and 26” conductors in a single deployment.

The modification proved highly successful and is now being incorporated into the next generation of Claxton internal cutting tools.

The Result

• 24 wells safely cut and recovered
• 24 cuts completed below mudline
• 6 additional cuts completed above the template
• Hydrocarbon risk fully assessed and mitigated
• No environmental discharge
• Zero Non-Productive Time (NPT)
• Deepest platform wells ever cut using abrasive cutting technology (206m total cut depth)

The project demonstrated Claxton’s ability to engineer bespoke solutions for complex conductor removal campaigns, combining tooling innovation, environmental risk control, and the operational efficiency of the xcalibre system in a single integrated execution.

38bdb4b2 9d58 498b b02c d76642e426d1 aspect ratio 31
xcalibre System Test before deployment
9bced8e6 6ad6 464a 9ee1 d76d7ef27911 aspect ratio 31
ROV Footage showing cut penetration subsea
PHOTO 2025 07 24 13 13

In numbers

  • 640ft Water Depth
  • 24 Conductors Cut & Recovered
  • 4 Hours Average Multi-String Cut Time
1cc837bc 2de0 4042 9920 90c24cf2d14f aspect ratio 31
xcalibre Tool Deployment on Guide Frame
D458c824 1f2b 4e34 bf64 b293bd5be2ac aspect ratio 31
Conductor Recovery to Vessel Laydown Frame