Bespoke Tool for Monopile Marine Growth Removal

Cs 2024 002 uk marine growth removal 3

Project details

Download PDF

Operated from Jack Up Vessel - 90 Minute cleaning time per monopile

The project was completed as part of a new wind farm installation off the North East coast of Scotland.

Monopiles had been driven into the seabed in advance of the transition piece being installed.

Cleaning was required to remove build up of marine growth / biofouling to ensure a seamless installation of this transition piece and grouting to the monopile.

Claxton designed a bespoke Marine Growth Removal (MGR) Tool to suit the 7.5m diameter profile.

The brand new tool was utilised across 19 monopiles in total, while deployed from the DEME Apollo Jack-Up Vessel.

Average clean time across the project was 90 minutes per monopile.

The operations were supported by Claxton’s offshore technicians, providing valuable MGR experience to the project and ensuring any issues could be overcome in a timely manner.

Cs 2024 002 uk marine growth removal 3 aspect ratio 31 23
MGR Tool onshore assembly
Cs 2024 002 uk marine growth removal aspect ratio 31 23
MGR Tool lifted onto monopile
Cs 2024 002 uk marine growth removal 2 aspect ratio 31 23
Installation of the transition piece onto a monopile, post cleaning project.
Decommissioning

In numbers

  • 7.5m Pile Diameter
  • 90mins Average Cleaning Time
  • 19 Monopiles Cleaned